Location: Michigan
Duration: 10 months
Manpower: average of 20 workers
Fabrication, delivery, on-site assembly and installation of more than 630 tons of steel structure, casing, filterhead, ductwork, stack, thermal insulation and cladding. Part of the project was also installation of modular heat exchangers for each line. MZP field routed and installed compressed air piping.