Location: Nevada
Duration: 3 months
Manpower: 8 workers
Demolition of old baghouse, ducts and fan. On-site assembly and installation of more than 100 tons baghouse filter, cyclone, ducts, stack and fan. Thermal insulation and cladding was supplied and installed by MZP. Part of this project was also field routing and installation of compressed air piping.